Ladys Island Park
- Have Park sign designed, pending approvals
- Park completed, expect opening in the month of June.
Burton Wells Phase II
- Park Completed
- Grand opening was held 5/18
Buckwalter Park Soccer Field III
- Field completed, available for use.
St. Helena Branch Library
- Masonry Block work complete.
- Stucco completed.
- Structural wood framing complete.
- Steel erection complete.
- Flat surface roofing complete.
- Standing seam roofing underway
- HVAC, Electrical system, above ground plumbing, 70% complete.
- Drywall underway.
- Window frame installation underway.
- Mid November 2012 completion date
DSN
- Project accepted
- Working with Attorney to complete project close out.
- Received preliminary commissioning report, facility is performing well.
Contract 43
- Jasmine Hall – completed
- Ballpark – completed
- Middlefield Circle – completed
- Stanley Road – on hold pending (ROW) right of way.
Contract 44
- Jessica – completed
- Ned Court – completed
- Foreman Hill Road – construction is 90% complete
- Fish Haul -- on hold pending (ROW) right of way.